Projects
Recent Projects
Grand Paris Express
Supply of Bridge Launching Girders Crane equipment for the new Paris Metro line (200 km), developed by VINCI Group. Eurosteel provided ~250 tons of various equipment for client DEAL S.r.l., including two 100m Launch Girders (each 2.5m high Box Beams).
- Paris Metro Line (Length): 200km
- Capacity: 250 tons
- Two of 100m Launch Girders (each 2.5m high Box Beams)
Cement Storage Silos
Production of cement silos and equipment in Porto-Romano, Durrës, for CIMSA Group (contracted by Berdica Cement). Turnkey design and execution by Eurosteel.
- Capacity: 3 x 5,000 tons (height: 45m)
- Loading: 300-350 tons/hr
- Unloading: 150 tons/hr
- Fabrication & Erection: 800 tons steel construction
JET Fuel Kastrati Group
Production and installation of JET fuel storage tanks for aircraft fuel, for Kastrati Group in the hydrocarbon storage park, Porto-Romano, Durrës.
- Capacity: 6 x 4,500 tons
- Fabrication & Erection: 735 tons steel construction
- -Dimensions: Ø 19,500 mm (height: 16,000 mm)
Vlora International Airport (VIA)
Production and installation of metal structures for the passenger terminal at Vlora International Airport (VIA), contracted by Mabetex Group (Lugano, Switzerland).
- Total Terminal Area: 18,000 m²
- On-Site Installation: 3,700 tons metal structures
- Produced & Processed: 900 tons metal structures
- Covering System (Kalzip Roof & Walls Technology): 16,000 m² roof + 2,000 m² walls steel construction
Clinker Storage Silos
Production and installation of clinker silos for Colacem Albania in Balldren, Lezhë.
- Capacity: 1 x 70,000 tons
- Height: 60m
- Fabrication & Erection: 500 tons equipment and steel construction